NextDC plunges 40% in a day: the real AI bottleneck is the power line, not contracts

ccerrato147 · x · 2026-10-25

The author argues the real AI data center bottleneck is the power line. NextDC, Australia's biggest listed data center developer, lost 40% in a day on Oct 21 after its utility paused grid upgrades at its Melbourne site until February — no power, no rent, and loans don't wait. Contracts don't help either: Nscale lists $103B of contracted work (85% from Microsoft and Anthropic), yet Microsoft walked away from its UK site on Oct 18. A contract doesn't connect power, finance chips, or put up buildings.