Rubin ramp slowed
- OSAT firm KYEC lowered its Q4 guidance (to 7–10% QoQ revenue growth) citing delayed mass production of a key customer's next-gen GPU, widely believed to be NVIDIA's Rubin; zephyrz9 says SK Hynix (mostly) and Micron dragged shipments down due to HBM4 yield issues.
- KYEC posted Q3 revenue of NT$12.14B (+9% QoQ, +31% YoY), with gross margin expected to dip to 36–37% in Q4.
Analyst view
- Morgan Stanley, BofA and Citi see it as deferral, not lost demand: delayed test orders should land in Q1 2027 with 10–15%+ QoQ revenue growth and 40%+ gross margin.
- Strong AI ASIC (Google TPU) and CPU (Vera/Axion/Cobalt) test demand offsets the GPU delay; KYEC's AI test capacity is expected to double in 2027, with full-year revenue up 40–53%.
- KYEC uses a consignment model where customers like NVIDIA fund key equipment, limiting capex and depreciation risk.
More from Infra
- Stable Diffusion Runs Fully Offline on a Galaxy S25 Ultra via QNN NPU — carrycooldude · 2026-11-06
- Every B300 Earns $8/Hour: Why the Grid Queue Gives Communities Massive Leverage Over AI Data Centers — Exponential View (Azeem Azhar) · 2026-11-06
- US has announced 3,969 AI data centers, with about 800 under construction — YvesMulkers · 2026-11-06
- AI's Next Architecture Question: Where Inference Should Actually Run — DavidLinthicum · 2026-11-06
- Alphabet's 13F reveals ~3M Qualcomm shares worth $548M, sparking chip partnership speculation — zephyr_z9 · 2026-11-06
- Floci: open-source local AWS emulator runs 120+ services in 24ms, free LocalStack alternative — thisguyknowsai · 2026-11-06