Compute contracts vs reality: Nscale has only 5% of contracted GPUs live, TeraWulf 12%

AccBalanced · x · 2026-10-25

A data-heavy thread on AI compute supply: demand is no longer in question—contracts are signed, and major neoclouds have contracted at least 2.5x more compute than they currently run. The key shift is prepayments: Nebius says 70% of deals signed last quarter included prepayments covering 50-60% of build cost, so late buildout now hurts customers too, not just data center companies.

Sold vs. live today (from earnings releases and SEC filings, data through Oct 23, 2026):

Takeaway: demand is contract-backed, but the delivery gap is far bigger than headlines suggest, and prepayment structures are starting to transfer buildout risk to buyers.