Tesla Optimus Factory Steel Structure 60% Done, Four Giga Press Foundations Poured

mitchdeg · x · 2026-11-28

Aerial update on Tesla's Optimus factory at Giga Texas: steel structure is roughly 60% complete and on track for finishing around end of March 2027, mostly four floors tall. Foundations for all four IDRA Giga Presses are poured — these will mass-produce robot parts — while site crews continue widening and reinforcing reclaimed ground.