Korea breaks ground on 1.2GW Donghae GS AI data center, ~15 trillion won investment

JungWooHa2 · x · 2026-11-28

The groundbreaking ceremony for the Donghae GS AI Data Center in Korea marks the first GW-scale AI DC since the government's mega-project announcement. Per the on-site board: total planned capacity 2.4GW with phase 1 at 1.2GW ('28–'29) and phase 2 at 1.2GW ('29–'30); 15 trillion won total investment including GPU budget; developed by GS AI Infraco on the Donghae inland industrial complex site. Timeline: government pre-feasibility announcement June '26, tri-party agreement July '26, construction start December '26, operation '28–'29.