Only 2% of announced 90GW self-powered data center capacity in US actually running
rohanpaul_ai · x · 2026-11-23
Bloomberg reports that "behind-the-meter" power for US data centers remains mostly on paper: developers have announced 90GW of dedicated power plants, but only 2GW — about 2% — is actually operational.
Why self-supply struggles: the grid provides redundancy across many plants and lines while a single on-site plant has none; AI workloads swing demand within seconds, enough to damage some generators; and solar plus batteries would need nearly 1,800 hectares to run a 100MW Texas data center just 98% of the year.
As a result, developers overbuild gas capacity, pay $100+/MWh versus $90 for grid power, and treat their own plants mainly as a bridge until grid connections arrive.
More from Infra
- Microsoft publishes Azure AI architecture design guide with Foundry Agent reference architectures — adnan_hashmi · 2026-11-23
- Bittensor's Subnet 92 claims a 'frontier JEV model' 200x faster than LLMs — markjeffrey · 2026-11-23
- Vercel CEO Rauch: 'free' ZDR stealth models look like industrial-scale data exfiltration — AccBalanced · 2026-11-23
- Lenovo's enterprise AI server sales surge 200%, outpacing cloud giants' 170% — shashib · 2026-11-23
- Australia's Spy Agency Now Treats Data Center Ownership as Foreign Interference Risk — rohanpaul_ai · 2026-11-23
- RTX Spark 18C vs M5 Pro/Max Benchmarks: 32% Faster Prompt Processing, But Apple Wins on Decode — Temporary-Size7310 · 2026-11-23