Maryland's 1,300 MW coal plant can't retire until a transmission line Sierra Club opposes gets built

paulnovosad · x · 2026-11-22

Matt Yglesias highlights a grid irony: Maryland wants to retire the 1,300 MW Brandon Shores coal plant, but replacement power requires new transmission lines that the Sierra Club and landowners are fighting. The BGE mitigation project spans 37 miles of 230kV/500kV lines plus 2 new substations, costing an estimated $1.1–1.69B with a late-2028/early-2029 target; a separate 67–70 mile PSEG line faces a Supreme Court petition from 60 landowners over eminent domain. A case study in how permitting friction slows both decarbonization and the power buildout AI demands.