Nvidia's $105B guarantee decoded: phase-by-phase, pays nothing yet
tengyanAI · x · 2026-11-18
- Responding to Colette Kress's claim that Nvidia's guarantee "doesn't exist anymore" on delayed buildouts, the author argues filings show Nvidia isn't abandoning neocloud partners.
- For the Ohio campus (with SB Energy), each guarantee only activates once its building is finished; the first isn't expected until fiscal 2029.
- Max exposure is $105B if every building completes; Nvidia has paid nothing on any guarantee so far—delay risk falls first on developers and lenders.
- Worth watching whether this phase-by-phase structure appears in future Nvidia neocloud deals.
More from Venture
- Debate: cheap, dispersed intelligence makes AI hard to be winner-take-all — jfischoff · 2026-11-29
- Product idea: cloud Android VMs and home WiFi proxies to make agents look human — Darpinian · 2026-11-29
- Situational Awareness's 167-Page Pitchbook: Leopold's Wife Is Dario Amodei's Chief of Staff — tzmartin · 2026-11-29
- Nearly half of Waymo's robotaxi miles in California are driven without passengers — Polymarket · 2026-11-29
- Debate: inference demand makes H100s more valuable while NVDA stock heads south — teortaxesTex · 2026-11-29
- Shopify Black Friday: AI-Referred Traffic Up 5.7x, $7.6B in Sales — juokaz · 2026-11-29