Satellite analysis: Huawei's Horinger campus has just 7% of Colossus 2's AI compute

Epoch AI · rss · 2026-11-13

Epoch AI used commercial satellite imagery and public sources to estimate the AI compute at Huawei's Horinger, Inner Mongolia data center, as a lens on the US-China compute gap. The North zone's sparse cooling equipment suggests it lacks power-dense AI servers; the four dense-cooling buildings total 286 MW of IT power, three already operational.

Assuming a four-month sale-to-deployment lag, they estimate 105,000 Ascend 910C and 8,000 910B chips are operational, equal to 81,000 H100-equivalents (90% CI: 36k–141k). For context, the 910C performs at 0.76 H100e while Nvidia's B200/B300 reach 2.5 H100e. Horinger is among China's largest AI data centers (only VNET Bayin Ulanqab and Huawei Wuhu likely rival it), yet holds just 7% of xAI's Colossus 2 capacity — about 14x smaller.

Outlook: a new South-zone building is expected operational by February 2028, growing campus compute over 70% to 141,000 H100e, but Colossus 2 is projected to reach at least 1.8 million H100e by 2028. Still, 10% of Horinger's compute (8,100 H100e) could train a DeepSeek-V4-Pro-scale model in a month; fully combined, a GPT-6 Astra-scale model would take about a year.

Original post →

More from Infra

Infra channel →