One Megawatt of AI Factory Costs $59M Up Front, Pays Back in Just Over Four Years

le_james94 · x · 2026-09-26

Summarizing Lecture 3 with Crusoe CEO Chase Lochmiller: one megawatt of AI factory costs about $59M up front — $19.2M building, $40M IT, of which $30M is GPUs. Rented as raw infrastructure it returns $15M a year, with payback landing a little over four years. The unit of account has shifted from dollars-per-GPU to dollars-per-megawatt.

The quoted Lecture 2 adds context: cost per token fell 99% in two and a half years while total spend went up — reasoning models and agents burn orders of magnitude more tokens, and H100 spot prices climbed through the whole decline. A fast chip is not a business.