71% Oppose, 261+ Moratoriums: Towns Freeze AI Data Center Permits Over Power and Water

shashib · x · 2026-09-04

The AI data center bottleneck is shifting from silicon to local permits, fought over who pays for power and water. Key figures: a March 2026 Gallup poll found 71% opposition to local AI data centers (48% strongly opposed) — higher than for nuclear plants; over 261 local moratoriums are in force; the Oracle-OpenAI project in Saline Township, MI adds 1.4 GW to DTE's grid; the fastest data center build took 90 days. The author argues data center firms are infrastructure companies unstaffed for local communications, and points to Meta's Richland Parish sales-tax check funding teacher bonuses (up to $50,000) and Ellendale, ND's $250/year household bill savings as the winning playbook versus national-strategy rhetoric.